Operations
Recently, and through the Measure C funds, CVCHS was awarded $6.7 million to spend on long-overdue facility improvements.  In August, the CVCHS Governing Board voted to approve the improvements listed below.  Work has already begun on several of these exciting projects!  Additionally, work on a previous Measure C project (building two new Chemistry Labs!) has also begun.

UPDATE:  Measure C is well underway at CVCHS!

1.  Our new Chemistry Labs will be open for classes at the start of second semester (beginning upon return from Winter Break)
2.  Our stadium upgrades will begin during Winter Break as well with the removal and replacement of our field turf and track surfaces.  Depending on weather, one or both of these items will be finished soon after Winter Break.
3.  All lockers on campus will be repaired, refurbished or replaced if needed.  The lockers will also be PAINTED inside and out which hasn't happened in many years.  Students will be asked to remove all personal belongings from their lockers prior to Break.
4.  This summer we will begin an exciting remodel and upgrade of the entire Gonsalves Stadium entry, concessions, restrooms and storage facilities!  Construction plans are being finalized now.
5.  Parking area surfacing to help accommodate the many students that drive to CV everyday.
6.  Expansion and remodel of our weight room facilities including new equipment.

Additional plans will be revealed as details become available.  This is an exciting time for Clayton Valley!

  CLAYTON VALLEY CHARTER HIGH SCHOOL--$6.7 MILLION PROJECT LIST

         TECHNOLOGY
  • Upgrade computers in all classrooms
  • Ensure computer labs are updated and classroom have necessary drops for computers
  • Add LCD projectors to remaining classrooms; all LCD installed in ceiling
  • Add copiers to all wings

         TRACK AND FIELD

  • Replacement of the existing turf with a new turf.
  • Resurfacing of the athletic track.
  • Site work for new snack shack to include restrooms.
  • Drainage improvements, concrete and asphalt pavement for entrance to stadium.
  • Auxiliary lighting at entrance to stadium and outer perimeter
  • Install sound system and metal security “awnings” at press box
  • Additional bleacher seating on “home” side of field (possibly concrete?)

          PHYSICAL EDUCATION FACILITIES UPGRADES

  • Add air conditions to locker room facilities and gymnasium
  • Upgrade/modernization of boys and girls locker rooms including new or refurbished lockers, flooring, benches, tile, etc.
  • Complete build-out of expanded weight room including all necessary equipment.

    ALL-SCHOOL LOCKERS

  • Repair/refurbish/replace all lockers
  • Electrostatic repainting

          MULTI-USE ROOM UPGRADE/EXPANSION

  • New furniture for MUR to include portable theater seating for Performing Arts events
  • Add air conditioning to existing multi-use room facilities
  • Facilities enhancements to expand and update performing arts space
  • New cafeteria tables

          ALL-SCHOOL EXTERIOR LIGHTING

  • Replace all exterior lighting with upgraded and stronger lighting

NOTE: Major categories are in “Bid Priority Order” while ordering of sub-projects may change based on final costs and timing of available funds.